Six stages · about 20 weeks

Sheet R-01

From first sketch to
first swim.

Every Retreat pool is built in the same six stages, in the same order, over about twenty weeks. This page sets out what happens in each one, what we need from you and what you hold at the end of it.

N°01 · The programme

Typical concrete pool · 20 weeks

Twenty weeks, drawn to scale.

A typical concrete pool, from the first site visit to handover. Stages overlap where they safely can, so engineering starts on the signed design while the certifier reviews the plans.

Book a site visit

Wk 00

Wk 02

Wk 04

Wk 06

Wk 08

Wk 10

Wk 12

Wk 14

Wk 16

Wk 18

Wk 20

01

Consult and survey

Weeks 1 to 2

02

Design and 3D

Weeks 2 to 6

03

Approvals and engineering

Weeks 6 to 10

04

Excavation and steel

Weeks 10 to 13

05

Shell and finish

Weeks 13 to 18

06

Handover and care

Week 20

Weeks counted from the first site visit

Rain and rock can add time · You hear about it that week

N°02 · The six stages

Same order · Every pool

Six stages, one crew.

Each stage ends with something you can hold: a brief, a drawing set, an approval, a signed steel inspection. You sign off one before we start the next.

Talk to a director

Stage 01 · Weeks 1 to 2

Consult and survey

It starts on your block, not in a showroom. A director walks the site with you and measures levels, access, soil, sun and the view lines from the rooms you use most. We ask who swims, how often, and what the garden around the pool should do.

Within a week of the visit we send a written brief and a budget range, so you know where you stand before any design work begins.

What you do

Walk the site with a director

Share plans, surveys or drawings

Give us a budget range

What we do

Survey levels, access and soil

Check overlays and easements

Write the brief and budget

You receive

A written brief and budget range

Stage 02 · Weeks 2 to 6

Design and 3D

James Whitcombe draws the pool by hand first, then models it in 3D with your house, levels and garden around it. You walk through the model with us, change what does not feel right, and we draw it again.

Once the design is settled, every line is priced. You receive a fixed-price contract with materials, equipment and the payment schedule set out in full, and a 5% deposit secures your place in the programme.

What you do

Two design meetings

Choose finishes and equipment

Sign and pay the 5% deposit

What we do

Hand drawings and a 3D model

Samples from our stone library

An itemised fixed price

You receive

A 3D design and fixed-price contract

Stage 03 · Weeks 6 to 10

Approvals and engineering

We lodge the building application through a private certifier and commission a structural engineer to design the shell for your soil and slope. If your block sits under a council overlay for flooding, coastal hazard or vegetation, we prepare those reports too.

Fencing is designed now, not after the pool is full, so it meets AS 1926.1 and passes inspection the first time. QBCC Home Warranty Insurance is in place before any work starts on site.

What you do

Sign the application forms

Approve the fence design

Confirm access with neighbours

What we do

Lodge with a private certifier

Engineer the shell and walls

Arrange home warranty cover

You receive

Building approval and engineering

Stage 04 · Weeks 10 to 13

Excavation and steel

Our own crew sets out the pool with pegs and string, then digs to the engineer’s levels. Spoil leaves site the same week, and rock is broken or sawn as we meet it rather than left for later.

Steel is tied to the engineering drawings and inspected before any concrete is ordered. Tom Hollis checks it himself, then the certifier signs it off. Plumbing and conduit go in at the same time.

What you do

Walk the set-out with us

Keep the site clear for machines

Approve any change to levels

What we do

Excavate to engineered levels

Tie steel and lay plumbing

Book the steel inspection

You receive

A signed steel inspection

Stage 05 · Weeks 13 to 18

Shell and finish

The shell is sprayed in a single day and cured before it carries stone or tile. While it cures we set the equipment pad, run the pipework and build the walls, steps and benches around the pool.

Coping and tile are laid by the same tradespeople on every Retreat pool. The interior goes on last, once the surrounds are finished, so it is never walked on in boots.

What you do

Sign off coping and tile on site

Choose lighting scenes

Plan planting with Claire

What we do

Spray and cure the shell

Lay coping, tile and interior

Fit equipment and lighting

You receive

An engineer’s sign-off on the shell

Stage 06 · Week 20

Handover and care

We fill the pool, balance the water over a week and book the certifier to inspect the fence before anyone swims. Then a director walks you through every valve, setting and switch, at the pool, not over the phone.

Twelve months later we come back to check the shell, the stone, the equipment and the water. Anything that needs adjusting is put right on that visit.

What you do

Walk the pool with a director

Learn the equipment and app

Pay the final 15%

What we do

Fill and balance the water

Book the fence inspection

Return at twelve months

You receive

Pool safety certificate and handover pack

N°03 · Paying for your pool

Five stages · One fixed price

You pay as the
work is done
.

Your fixed price is split into five stage payments. Each one falls due when that work is complete and, where it applies, inspected. You never pay ahead of the work on site.

Queensland deposit cap

Queensland caps deposits at 5% on residential building contracts over $20,000. Ours is 5%, due when you sign.

Stage

Paid when

Share

01

Deposit

On signing the fixed-price contract

5%

02

Excavation and steel

When the steel is tied and signed off by the certifier

25%

03

Shotcrete shell

When the shell is sprayed

30%

04

Coping, tile and interior

When the interior is applied

25%

05

Practical completion

At handover, with the pool safety certificate

15%

Total

Your fixed price, with nothing added after signing

100%

N°04 · Approvals and compliance

Included in every fixed price

Approved before we dig.

Every approval below is part of your fixed price. We lodge them, follow them up and hand you the certificates at the end.

Pool fencing rules, explained

Building approval

Private certifier, weeks 6 to 10

Every pool needs a building approval. We lodge it through an independent private certifier, who inspects the steel, the fence and the finished pool.

Structural engineering

Designed for your soil and slope

An engineer designs the shell, steel and any retaining walls from a soil test. Sandy coastal blocks and sloping hinterland sites are engineered differently.

Pool safety certificate

Issued before the first swim

The certifier inspects the barrier once the pool is filled. In Queensland the pool is then listed on the state pool safety register.

Fencing to AS 1926.1

Drawn with the pool, not after it

Gate swing, heights and non-climbable zones are part of the design. Glass, steel or masonry, the fence is built to pass the first inspection.

QBCC Home Warranty Insurance

In place before work starts

Queensland residential pools carry QBCC Home Warranty Insurance. Your certificate arrives before our crew starts on site.

Council overlays

Flood, coastal and vegetation

Some blocks sit under overlays from the City of Gold Coast, Brisbane City Council or the Byron and Tweed shires. We check at the first visit and prepare any reports they need.

N°05 · Warranty and aftercare

Lifetime · Seven years · Twelve months

Still ours after handover.

A pool should outlast the house beside it. These warranties and visits come with every Retreat pool, in writing, as part of the contract.

Read our warranty terms

01

Lifetime structural

The concrete shell carries a lifetime structural warranty. It is engineered for your site, inspected before the pour and built to hold its shape for as long as the house stands.

02

Seven years on workmanship

Coping, tile, plumbing and the work of our own crew are covered for seven years. Pumps, heaters and chlorinators carry their manufacturers’ warranties, registered in your name at handover.

03

A return visit at twelve months

A director comes back a year after handover to check the shell, stone, grout, equipment and water. Anything that needs adjusting is put right on that visit.

Handover pack

Everything in one folder.

The paperwork you need to own, insure and one day sell the pool, bound in a folder and sent as PDFs on the day we hand over.

01

Building approval and final inspection certificate

02

Pool safety certificate

03

Engineer’s design and steel inspection

04

QBCC Home Warranty Insurance certificate

05

As-built drawings with pipe and cable runs

06

Equipment manuals and registered warranties

07

A care guide for your stone and interior

08

Your twelve-month visit, already booked

N°06 · Client words

4.9 from 126 Google reviews

“The programme they drew up at our first meeting was the one we got, give or take two days of rain. Luke sent a photo and a few lines every Friday for twenty weeks.”

Anna and David Reyes

Currumbin Valley · Reflection pool · 2024

Read all 126 reviews

N°07 · Questions

Questions about
the process.

What people ask before they sign. Anything else, call the studio on 07 5576 3480.

All questions

How long does a concrete pool take to build?

About twenty weeks from the first site visit to handover for a typical concrete pool. Spas and plunge pools take eight to fourteen weeks and infinity edges up to twenty-four. Rain, rock and council overlays can add time, and we tell you the week it happens.

Do I need to be home during the build?

No. Most clients are at work during the day and some live elsewhere while we build. We need access, power and water, and a director meets you on site for each sign-off.

When do I pay, and how much up front?

A 5% deposit when you sign the fixed-price contract, then four stage payments as each stage is completed and, where it applies, inspected. You never pay ahead of the work on site.

Who handles council and approvals?

We do. The building approval, engineering, fence certification and any council overlay reports are lodged by us and included in your fixed price.

What happens if it rains?

Excavation and the shell spray stop in heavy rain, and the programme moves by the days lost. You hear about it in that week’s update, with the new dates.

Can we change the design once building starts?

Yes. Structural changes can be made up to the steel inspection and finishes up to tiling. Every change is priced in writing before we make it, so the fixed price stays fixed.